TechCentral / Henry Schein
Implementation PlaybookDSO · Group Practice

TechCentral / Henry Schein

Step-by-step implementation guide — pre-implementation checklist, onboarding, staff training, go-live runbook, and ROI tracking.

TechCentral / Henry Schein — Implementation Playbook (DSO)

TechCentral / Henry Schein Dental IT & Cybersecurity Implementation Playbook

For Dental Service Organizations (15–50 Locations)


1. Executive Summary

What This Tool Does

TechCentral by Henry Schein delivers enterprise-grade IT infrastructure management and cybersecurity protection purpose-built for dental environments. The platform provides centralized monitoring of network health, endpoint security, automated threat detection, data backup and disaster recovery, and HIPAA-compliant security protocols across distributed dental locations—all managed through a unified dashboard with 24/7 support.

Why DSOs Specifically Benefit from Dental IT & Cybersecurity AI

At scale, DSOs face exponentially greater cybersecurity risk than single practices. A breach at one location can cascade across your network, compromise patient data enterprise-wide, and trigger regulatory penalties multiplied across affected locations. TechCentral's centralized approach transforms IT from a fragmented, location-by-location cost center into a strategic asset:

  • Scale Advantage: Unified security policies deployed once, enforced everywhere—eliminating the inconsistency of 15–50 different IT setups
  • Standardization: Consistent hardware lifecycle management, patch deployment, and compliance protocols reduce audit complexity and liability
  • Data Aggregation: Real-time visibility into network health, threat vectors, and incident response across all locations from a single pane of glass
  • Economies of Scale: Enterprise licensing, centralized support, and standardized configurations reduce per-location IT costs by 20–35%

Expected Timeline: Decision to Full Deployment

Portfolio Size Pilot Phase Wave Deployment Full Deployment
15–25 locations 3–4 weeks 6–8 weeks 12–14 weeks total
26–40 locations 3–4 weeks 10–12 weeks 16–18 weeks total
41–50 locations 4–5 weeks 12–14 weeks 20–22 weeks total

2. Pre-Implementation Checklist (Weeks 1–2)

Technical Requirements

Hardware Requirements

☐ Audit current workstation inventory across all locations (age, specs, OS version) ☐ Identify workstations requiring replacement (>5 years old or Windows 10 pre-21H2) ☐ Verify minimum 8GB RAM per clinical workstation, 16GB for server/imaging workstations ☐ Confirm UPS (battery backup) presence at each location for critical systems ☐ Document existing firewall hardware make/model/firmware version at each site

Network Requirements

☐ Minimum 100 Mbps symmetric internet at each location (500 Mbps recommended for imaging-heavy practices) ☐ Business-class internet with static IP or DHCP reservation capability ☐ Network diagram for each location documenting all connected devices ☐ Current WiFi infrastructure assessment (separate guest vs. practice networks required) ☐ ⚠️ VPN or SD-WAN infrastructure audit—critical for centralized management

Software Requirements

☐ Complete software inventory per location (PMS, imaging, specialty applications) ☐ Current antivirus/endpoint protection documentation (for removal/migration planning) ☐ Windows Server versions and patch levels for on-premise servers ☐ Active Directory or local account structure documentation ☐ Current backup solution inventory

Integration Requirements

☐ PMS system identification per location (Dentrix, Eaglesoft, Open Dental, other) ☐ PMS version numbers and recent update history ☐ Imaging system identification (Dexis, Schick, Carestream, etc.) ☐ HL7/API capabilities of current systems ☐ Current clearinghouse and e-prescribing integrations

Vendor Onboarding Steps

Key Contacts to Establish

☐ 🔵 Henry Schein TechCentral Account Executive (primary relationship) ☐ 🔵 Technical Implementation Lead (assigned post-contract) ☐ 🔵 24/7 Support escalation contacts and SLA documentation ☐ 🔵 HIPAA/Compliance specialist for BAA and audit support ☐ 🔵 Enterprise Account Manager for ongoing strategic reviews

Onboarding Actions

☐ 🔵 Schedule enterprise kick-off call (90 minutes minimum) — Time estimate: Week 1, Day 1–2 ☐ 🔵 Request and review enterprise implementation timeline from vendor — Time estimate: 2 hours ☐ 🔵 Obtain complete technical documentation and system requirements — Time estimate: Vendor delivers within 48 hours ☐ 🔵 Review and execute Business Associate Agreement (BAA) — Time estimate: Legal review 3–5 days ☐ 🔵 Confirm licensing model (per-user, per-device, per-location, or hybrid) — Time estimate: 1 hour ☐ Request case studies from similar-sized DSO deployments — Time estimate: Vendor delivers within 1 week

Data/Access Prerequisites

Credentials and Access

☐ Domain admin credentials or equivalent for all locations ☐ PMS administrator access across all instances ☐ Current hosting provider credentials (if cloud/hybrid infrastructure) ☐ Email/Microsoft 365 or Google Workspace admin access ☐ Existing VPN credentials and configuration files ☐ ⚠️ Document all third-party IT vendor relationships requiring coordination or termination

Data Preparation

☐ Export current network topology documentation ☐ Compile existing security audit reports (if any) ☐ Document HIPAA Risk Assessment history and findings ☐ Identify any past security incidents requiring disclosure ☐ Catalog all business-critical data locations and backup schedules

Enterprise-Level Requirements

Network Standards Across Locations

☐ 🟣 Define enterprise network architecture standard (hub-and-spoke, mesh, hybrid) ☐ 🟣 Establish minimum bandwidth requirements as policy ☐ Document preferred ISP contracts and standardization opportunities ☐ Define standardized VLAN structure (clinical, guest, IoT, administrative) ☐ Establish DNS and DHCP standards

Hosting Architecture Decision

☐ 🟣 Determine centralized vs. location-level hosting model:

  • Centralized: Single data center or cloud tenant, all locations connect remotely
  • Hybrid: Central management with local caching/redundancy
  • Distributed: Location-level servers with centralized monitoring ☐ Document latency requirements based on clinical workflow needs ☐ Define data residency and sovereignty requirements if multi-state

Identity and Access Management

☐ 🟣 Single Sign-On (SSO) requirements and existing identity provider (Azure AD, Okta, etc.) ☐ Define role-based access control (RBAC) structure ☐ Multi-factor authentication (MFA) policy and rollout plan ☐ Privileged access management requirements ☐ Credential rotation and password policy standards

Centralized Credentialing

☐ Unified device naming convention (e.g., [LocationCode]-[DeviceType]-[Number]) ☐ Standardized local admin account structure ☐ Service account inventory and management plan ☐ Certificate management strategy

Stakeholder Alignment Map

Board/Investors (Inform + Approve Budget)

Stakeholder Communication Need Approval Required Timeline
Board of Directors Strategic rationale, ROI projection, risk mitigation value ☐ Budget approval Pre-contract
Private Equity Sponsor Alignment with portfolio value creation thesis ☐ Capital expenditure sign-off (if above threshold) Pre-contract

C-Suite (Decision + Sponsorship)

Stakeholder Role in Implementation Approval Required Timeline
CEO Executive sponsor, escalation point ☐ Final go-decision Week 1
COO/VP Operations Operational owner, rollout oversight ☐ Timeline and resource allocation Week 1
CFO Budget holder, ROI tracking owner ☐ Contract and payment terms Week 1
Chief Dental Officer Clinical workflow impact assessment ☐ Clinical disruption sign-off Week 1
CIO/IT Director Technical lead, vendor liaison ☐ Technical architecture Week 1

Regional Managers (Execute + Cascade)

Stakeholder Role in Implementation Communication Need Timeline
Regional Directors Wave coordination, local escalation Detailed rollout calendar Week 2
Area Managers Champion identification, readiness validation Location-specific timelines Week 2

Location-Level (Participate + Adopt)

Stakeholder Role in Implementation Communication Need Timeline
Office Managers Local coordination, staff communication Go-live checklist, training schedule Week 2–3
Providers (Dentists, Specialists) End user adoption Impact summary, workflow changes Week 3
Clinical Staff End user adoption Training schedule, what changes Week 3
Front Desk/Admin End user adoption System access, troubleshooting basics Week 3

⚠️ Common Failure Point: Insufficient regional manager buy-in creates rollout delays. Schedule dedicated briefings before any location communication.

Baseline Metrics to Capture

⚠️ Standardize Measurement Methodology Before Data Collection

Metric Category Specific Metric Measurement Method Target Source
Security Posture Number of security incidents (past 12 months) Incident log review + staff interviews IT records/vendor reports
Security Posture Time to detect security incidents Incident timestamp analysis IT ticketing system
Security Posture Time to resolve security incidents Incident closure analysis IT ticketing system
Security Posture Patch compliance rate (% systems current) Automated scan or manual audit Endpoint management tool
Operational Impact IT-related downtime hours per location per month Downtime log or staff survey Office manager records
Operational Impact Number of IT support tickets per location per month Help desk data Ticketing system
Operational Impact Mean time to resolution for IT tickets Help desk data Ticketing system
Operational Impact Staff hours spent on IT troubleshooting Time tracking or estimate Manager interviews
Financial Current IT spend per location (managed services, break-fix, hardware) AP analysis Finance
Financial Estimated cost of downtime per hour Production report analysis PMS + finance
Compliance Last HIPAA Risk Assessment date Compliance records Compliance officer
Compliance Outstanding HIPAA remediation items Risk assessment review Compliance officer
Backup/Recovery Backup success rate (% successful backups) Backup logs IT records
Backup/Recovery Recovery time objective (RTO) – actual vs. required DR test results IT documentation
User Experience Staff satisfaction with IT (1–10 scale) Standardized survey Direct survey

☐ Create standardized data collection template distributed to all office managersTime estimate: 4 hours to create, 1 week for collection

☐ 🟣 Baseline data review and sign-off by C-suite before proceedingTime estimate: 2-hour review meeting


3. Location Readiness Assessment

Scoring Framework

Score each factor 1–5 using the criteria below. Total composite score ranges from 5 (not ready) to 25 (highly ready).

Factor 1: IT Infrastructure Maturity (Weight: High)

Score Criteria
5 <3 year old hardware, current OS/PMS versions, fiber internet >250 Mbps, enterprise firewall, documented network
4 3–4 year hardware, OS/PMS within 1 version of current, 100+ Mbps internet, business firewall
3 4–5 year hardware, OS/PMS 2 versions behind, 50–100 Mbps internet, consumer-grade firewall
2 5–6 year hardware, outdated OS requiring upgrades, <50 Mbps internet, basic router security
1 >6 year hardware, unsupported OS, unreliable internet, no firewall, undocumented network

Factor 2: Staff Tenure and Adaptability (Weight: Medium-High)

Score Criteria
5 <15% annual turnover, documented tech training program, history of successful tech adoption, avg tenure >3 years
4 15–25% turnover, some tech training, 1–2 successful tech rollouts, avg tenure 2–3 years
3 25–35% turnover, informal training, mixed tech adoption history, avg tenure 1–2 years
2 35–50% turnover, minimal training, tech adoption challenges, avg tenure <1 year
1 >50% turnover, no training program, failed tech rollouts, constant staffing changes

Factor 3: Patient Volume (Weight: Medium)

Score Interpretation Risk/Reward
5 Top 20% volume location Highest impact, highest stakes—ideal for Wave 2 once proven
4 60–80th percentile volume Strong impact, manageable risk—good Wave 1 candidate
3 40–60th percentile volume Moderate impact and risk—flexible wave placement
2 20–40th percentile volume Lower impact, good for learning—Wave 1 pilot candidate
1 Bottom 20% volume location Limited impact—appropriate for final waves or specialized attention

Note: For pilot selection, mid-volume locations (scores 2–4) are preferable—enough activity to validate but lower blast radius if issues arise.

Factor 4: Tech Stack Compatibility (Weight: High)

Score Criteria
5 PMS and imaging fully compatible, existing TechCentral/Henry Schein relationship, standardized stack
4 PMS on supported list, imaging compatible, straightforward integration path
3 PMS supported with some customization needed, imaging may require updates
2 PMS supported but outdated version requiring upgrade, imaging compatibility unknown
1 PMS not on supported list, significant integration work required, legacy systems

Factor 5: Local Champion Availability (Weight: Medium-High)

Score Criteria
5 Tech-forward provider AND office manager, both willing to champion, prior implementation experience
4 Willing office manager champion with tech comfort, provider supportive
3 Identified champion candidate, moderate tech comfort, requires development
2 No obvious champion, will need to identify or develop during rollout
1 Staff resistant to change, no champion candidates, low engagement

Composite Score Calculation

Factor Location A Location B Location C ...
IT Infrastructure (×1.2) ___ × 1.2 = ___ × 1.2 = ___ × 1.2 =
Staff Adaptability (×1.1) ___ × 1.1 = ___ × 1.1 = ___ × 1.1 =
Patient Volume (×1.0) ___ × 1.0 = ___ × 1.0 = ___ × 1.0 =
Tech Stack (×1.2) ___ × 1.2 = ___ × 1.2 = ___ × 1.2 =
Local Champion (×1.1) ___ × 1.1 = ___ × 1.1 = ___ × 1.1 =
Weighted Total ___/28 ___/28 ___/28

Rollout Sequence Recommendation

Composite Score Recommended Wave Rationale
23–28 Wave 1 (Pilot) High readiness, ideal proving ground
18–22 Wave 2 Strong foundation, benefit from pilot learnings
13–17 Wave 3 May need pre-work, benefit from refined playbook
8–12 Wave 4 (or remediation) Significant prep required, consider infrastructure upgrades first
5–7 Defer/Remediate Not ready—create remediation plan before inclusion

☐ Complete readiness assessment for all locationsTime estimate: 30–45 minutes per location, 2–3 days total for 25 locations

☐ 🟣 Present readiness scores and recommended wave structure to C-suite for approvalTime estimate: 1-hour presentation + discussion


4. Rollout Strategy

Wave Structure Recommendation

Wave Architecture Overview

┌─────────────────────────────────────────────────────────────────┐
│  WAVE 0: Infrastructure Prep (Weeks 1–3)                        │
│  All locations: Baseline, assessments, pre-requisite remediation│
└─────────────────────────────────────────────────────────────────┘
                              ↓
┌─────────────────────────────────────────────────────────────────┐
│  WAVE 1: Pilot (Weeks 4–6)                                      │
│  2–3 locations: Full deployment, intensive support, learning    │
└─────────────────────────────────────────────────────────────────┘
                              ↓ Go/No-Go Gate
┌─────────────────────────────────────────────────────────────────┐
│  WAVE 2: Expansion (Weeks 7–10)                                 │
│  5–8 locations: Refined playbook, train-the-trainer activated   │
└─────────────────────────────────────────────────────────────────┘
                              ↓ Go/No-Go Gate
┌─────────────────────────────────────────────────────────────────┐
│  WAVE 3: Scale (Weeks 11–16)                                    │
│  10–15 locations: Parallel deployments, distributed support     │
└─────────────────────────────────────────────────────────────────┘
                              ↓ Go/No-Go Gate
┌─────────────────────────────────────────────────────────────────┐
│  WAVE 4: Completion (Weeks 17–22)                               │
│  Remaining locations: Final deployments, edge cases             │
└─────────────────────────────────────────────────────────────────┘

Wave 1 Pilot Selection Criteria

Select 2–3 locations meeting ALL of the following:

Must-Have Criteria

☐ Composite readiness score ≥20 ☐ Office manager willing to serve as active champion ☐ Lead provider supportive of initiative ☐ IT infrastructure requires no major pre-work (score ≥4) ☐ ⚠️ NOT your highest-volume flagship location (manageable risk) ☐ NOT your lowest-performing location (needs to represent "normal")

☐ Geographic proximity to each other (enables single-trip support visits) ☐ Different PMS systems represented (tests integration breadth) ☐ Mix of general and specialty providers (tests workflow variations) ☐ Strong regional manager overseeing these locations ☐ Recent positive experience with change/new technology

Diversity Requirement

☐ At least one urban and one suburban location (if applicable) ☐ At least one single-provider and one multi-provider location

Detailed Wave Timeline

Wave 1: Pilot (3 weeks per location, 2–3 locations concurrent)

Week Activities Responsible
Week 4, Days 1–2 🔵 On-site infrastructure assessment and remediation TechCentral + Local IT
Week 4, Days 3–5 Hardware deployment and network reconfiguration TechCentral
Week 5, Days 1–2 Software installation and initial configuration TechCentral
Week 5, Days 3–5 Integration testing (PMS, imaging, backup) TechCentral + Champions
Week 5–6 Champion training (intensive, on-site) TechCentral
Week 6 Parallel run with legacy systems Location team
Week 6, Day 5 Go-live All
Week 7–9 Intensive monitoring, daily check-ins Central team

Buffer between Wave 1 and Wave 2: 1 week minimum

  • Document all issues encountered and resolutions
  • Update configuration templates
  • Revise training materials based on feedback
  • 🟣 Present Wave 1 learnings to leadership

Wave 2: Expansion (2 weeks per location, 5–8 locations concurrent)

Week Activities Responsible
Week 10, Days 1–3 Remote infrastructure prep and hardware staging Central IT + Regional
Week 10, Days 4–5 Remote software deployment (leveraging standardized config) Central IT
Week 11, Days 1–2 🔵 Remote integration validation TechCentral + Champions
Week 11, Day 3 Champion training (remote, using certified Wave 1 champions) Central team + Wave 1 Champions
Week 11, Day 4 Parallel run (abbreviated—lessons learned applied) Location team
Week 11, Day 5 Go-live All
Week 12–13 Monitoring with decreasing intensity Central team

Buffer between Wave 2 and Wave 3: 1 week minimum

Wave 3: Scale (2 weeks per location, 10–15 locations in parallel sub-waves)

Week Activities Responsible
Week 14–15 Sub-wave 3A: 5–7 locations Regional team lead
Week 16–17 Sub-wave 3B: 5–8 locations Regional team lead

Wave 4: Completion (Variable timeline based on remediation needs)

Week Activities Responsible
Week 18+ Remaining locations, including any requiring pre-work Central + Regional
Ongoing Edge case resolution, low-readiness location support All

Go/No-Go Criteria

Criteria to Advance to Next Wave

Category Green (Go) Yellow (Conditional Go) Red (No-Go)
Technical Stability <2 critical issues, all resolved within 24 hours 2–4 critical issues, all resolved within 72 hours >4 critical issues OR any unresolved >72 hours
Integration Success All integrations functional, <5% transaction errors Minor integration gaps, workarounds documented Major integration failure affecting operations
User Adoption >80% staff trained, >70% reporting comfort 60–80% trained, 50–70% comfort <60% trained OR <50% comfort
Champion Effectiveness Champions resolving 70%+ of Tier 1 issues Champions resolving 50–70% of Tier 1 issues Champions overwhelmed, escalating majority
Operational Impact No increase in IT-related downtime <2 hours additional downtime during transition >2 hours downtime OR patient care impact

🟣 Go/No-Go Decision Authority: COO with input from CIO and Regional Manager

⚠️ Rollback Plan

If a wave fails Go/No-Go criteria:

  1. Immediate Actions (Day 1)

    • Pause all pending deployments in current and future waves
    • Activate vendor escalation to Implementation Lead and Account Executive
    • Communicate status to all affected location champions and regional managers
  2. Diagnostic Phase (Days 2–5)

    • Root cause analysis with vendor
    • Document specific failure points and contributing factors
    • Assess whether issues are location-specific or systemic
  3. Remediation Options

    Scenario Recommended Action
    Location-specific issue Remediate affected location(s), proceed with wave for unaffected
    Configuration/template issue Revise templates, re-test in controlled environment, restart wave
    Integration issue 🔵 Vendor engagement required, pause until resolution verified
    Training/adoption issue Extend parallel run, intensify training, re-assess champions
    Systemic issue 🟣 Full stop, executive review required before proceeding
  4. Communication Protocol

    • Daily updates to C-suite during pause
    • Weekly updates to board if pause exceeds 2 weeks
    • Transparent communication to locations: "We're getting this right for you"

5. Configuration & Integration (Weeks 2–3)

Practice Management System Integration

Dentrix Integration

☐ Step 1: Version VerificationTime estimate: 15 minutes

  • Confirm Dentrix version (G7 or later required for full integration)
  • Document current Dentrix server configuration (local vs. hosted)
  • Verify Dentrix user accounts with appropriate permissions

☐ Step 2: 🔵 TechCentral Connection SetupTime estimate: 1–2 hours

  • Install TechCentral agent on Dentrix server
  • Configure database connection parameters
  • Enable API access (Dentrix API subscription required)
  • Document connection credentials in secure vault

☐ Step 3: Backup IntegrationTime estimate: 30 minutes

  • Configure automated backup of Dentrix database
  • Set backup retention schedule per enterprise policy
  • Test backup restoration in isolated environment

☐ Step 4: Integration ValidationTime estimate: 1 hour

  • Verify patient data accessibility (read-only)
  • Confirm appointment schedule synchronization
  • Test reporting integration
  • Document any compatibility limitations

Eaglesoft Integration

☐ Step 1: Version VerificationTime estimate: 15 minutes

  • Confirm Eaglesoft version (21 or later required)
  • Document database server location and credentials
  • Verify network accessibility from TechCentral management server

☐ Step 2: 🔵 Database ConnectionTime estimate: 1–2 hours

  • Configure SQL connection to Eaglesoft database
  • Set appropriate read permissions
  • Enable secure connection protocols

☐ Step 3: Backup ConfigurationTime estimate: 30 minutes

  • Configure database backup schedule
  • Enable transaction log backups for point-in-time recovery
  • Verify backup file locations and retention

☐ Step 4: Integration ValidationTime estimate: 1 hour

  • Test connectivity stability
  • Verify data synchronization accuracy
  • Document integration points and limitations

Open Dental Integration

☐ Step 1: Version VerificationTime estimate: 15 minutes

  • Confirm Open Dental version (current stable release recommended)
  • Document MySQL server location and credentials
  • Verify eConnector status if using cloud features

☐ Step 2: 🔵 API/Database SetupTime estimate: 1 hour

  • Enable Open Dental API access
  • Configure TechCentral database connector
  • Set up secure credentials storage

☐ Step 3: Backup IntegrationTime estimate: 30 minutes

  • Configure MySQL backup strategy
  • Set backup schedule aligned with enterprise standards
  • Test restoration process

☐ Step 4: Integration ValidationTime estimate: 45 minutes

  • Verify API connectivity
  • Test data access functions
  • Document any customization requirements

Imaging System Integration

General Imaging Integration Steps (Dexis, Schick, Carestream, Apteryx, etc.)

☐ Step 1: System InventoryTime estimate: 30 minutes per location

  • Document imaging software name, version, and licensing
  • Identify image storage location (local vs. network)
  • Map imaging sensor hardware and workstation assignments

☐ Step 2: Storage and BackupTime estimate: 1 hour

  • Configure imaging archive backup (typically large files—plan accordingly)
  • Set appropriate retention policies per regulations
  • Enable offsite replication for disaster recovery

☐ Step 3: ⚠️ Network OptimizationTime estimate: 1–2 hours

  • Verify network bandwidth supports image transfer requirements
  • Configure QoS for imaging traffic if necessary
  • Test image capture and retrieval times

☐ Step 4: DICOM Compliance (if applicable) — Time estimate: 30 minutes

  • Verify DICOM compatibility for imaging archival
  • Configure PACS integration if using centralized imaging

Test Environment Setup

☐ Create isolated test environment replicating productionTime estimate: 2–3 days

  • Deploy TechCentral management console in test instance
  • Connect 1–2 representative test workstations
  • Install test PMS instances (use de-identified data only)
  • Configure imaging with test sensors

Validation Checklist

Test Category Specific Test Pass Criteria Result
Connectivity Agent to management console <5 second heartbeat
Monitoring Workstation health check All metrics reporting
Backup Full backup execution Completes without error
Backup Restoration test Data integrity verified
Security Endpoint protection active Threats blocked in test
Security Patch deployment Test patch installs correctly
PMS Integration Database connectivity Stable over 24 hours
Imaging Backup of image archive Files recoverable
Alerting Test alert generation Alerts received by NOC and local
Reporting Dashboard population Accurate data displayed

Data Migration / Historical Ingestion

☐ ⚠️ Historical Security Log IngestionTime estimate: Variable, 1–3 days

  • Export security logs from previous antivirus/endpoint solution
  • Import relevant historical data into TechCentral (vendor-assisted)
  • Verify data integrity post-migration

☐ Configuration MigrationTime estimate: 1–2 days

  • Export existing firewall rules
  • Document current backup schedules and retention
  • Migrate applicable configurations to TechCentral management

Security and HIPAA Compliance Verification

Enterprise-Level HIPAA Checklist

Requirement Verification Method Documentation
Business Associate Agreement ☐ 🔵 Executed BAA with Henry Schein TechCentral File in compliance repository
Data Encryption at Rest ☐ Verify AES-256 encryption for stored data TechCentral security documentation
Data Encryption in Transit ☐ Verify TLS 1.2+ for all data transmission Network configuration audit
Access Controls ☐ Role-based access implemented in TechCentral console RBAC policy document
Audit Logging ☐ All access logged with user ID, timestamp, action Log retention verification
Automatic Logoff ☐ Session timeout configured per policy (typically 15 min) System configuration
Unique User IDs ☐ No shared accounts, all users uniquely identified User account audit
Emergency Access ☐ Break-glass procedure documented and tested Emergency access policy
**

AI-generated implementation guide based on public vendor information. Verify specifics directly with TechCentral / Henry Schein.